Permit Types
Municipal Consent - Hamilton Township ($50.00)
Municipal Consent is the municipality’s authorization for a utility to occupy a specific location(s) within the municipalities right-of-way. Municipal Consent will only be issued to utility companies, commissions, agencies, other municipalities, or private applicants who have a municipal access agreement with the municipality applied to. The project of adding or modifying the plant is often subject to a Work in Right-of-Way permit.
Road Cut Permit - Hamilton Township ($200.00)
A Road Cut Permit relates to any activity that involves the cutting, excavation, boring, filling, additions, or altering in any way, roadways, curbs, sidewalks, boulevards, ditches, trails, and other areas within the right-of-way.
Drawings are to be in compliance with the Ontario Traffic Manual (OTM).
Please note, deposit will be required
Road Occupancy Permit - Hamilton Township ($200.00)
A Road Occupancy Permit relates to any activity that results in traffic disruption, including bins, materials and equipment blocking lanes or temporary impacting the flow of traffic.
Drawings may need to be provide to provide additional details. A traffic Control Plan in compliance with the Ontario Traffic Manual (OTM), Book 7, Temporary Conditions for traffic plan instructions, will be required.
Work in Right-of-Way Permit - Hamilton Township ($100.00)
A Work in Right-of-Way Permit relates to any activity that does not result in any traffic disruptions and that the work is within the Township's right-of-way, such as but not limited to, boulevards, ditches, trails, brushing, etc. A traffic plan in compliance with the Ontario Traffic Manual (OTM), Book 7, Temporary Conditions for traffic plan instructions, may be required.